Ventilation Airflow Testing: What Happens During Commissioning?
A practical guide to the checks, measurements and records that help show whether a mechanical ventilation system is ready for use.
Freshly installed equipment can look complete while still needing adjustment. A fan may be powered, yet a long or restricted duct could limit the air reaching the outside. A multi-room system may move plenty of air overall but distribute it unevenly. A boost switch may work without residents understanding when to use it. Ventilation airflow testing helps turn an installation into a checked, usable system.
This article explains the process for homeowners, landlords, housing providers and project teams. The exact checks depend on the ventilation strategy, the scope of work, the building and the regulatory route. It is therefore a guide to the questions and records to expect, not a universal commissioning specification.
What ventilation commissioning actually means
Commissioning is not a single reading and it is not the same as switching the fan on. It is a sequence that checks whether the installed system matches the design, operates through its intended modes and delivers the required performance at the relevant terminals. When an adjustment is needed, the system is set and tested again so the final record describes the commissioned condition.
Inspect
Confirm that equipment, terminals, ductwork, controls and access points are present and sensibly installed.
Set and balance
Adjust the system so that air is distributed in line with the design rather than simply maximising every fan speed.
Measure and record
Test relevant operating modes, document results and retain the settings that produced them.
The process varies by system. An intermittent bathroom fan, a continuous decentralised extract fan, centralised mechanical extract ventilation and mechanical ventilation with heat recovery do not have identical controls or test points. The first question should therefore be: what ventilation strategy was designed for this property?
What should be checked before airflow is measured?
A meter cannot compensate for an incomplete installation. Before taking final readings, the commissioning person should be able to establish that the system is complete, accessible and configured for the intended test condition. Relevant checks may include the following.
The installed system matches the design
Fans, terminals and controls should correspond with the specification or agreed variation. For a ducted system, routes, sizes and fittings influence resistance. A last-minute reroute, crushed flexible duct or unexpectedly long run can change performance even when the visible grille looks correct.
Air can travel through the building
Extract ventilation removes air from wet rooms, but replacement air needs a planned route. Depending on the strategy, this may involve background ventilators, supply terminals and transfer paths beneath or through internal doors. Commissioning should not treat each extract point as an isolated appliance.
Terminals and ductwork are ready
Valves should be fitted, ducts connected and external terminals unobstructed. Filters must be installed where the system requires them. Access panels and maintenance points should remain usable. Temporary protection, packaging or construction dust should not be left to distort the final reading.
Controls can be identified
The tester needs to know which mode is being measured. A system may have normal, boost, purge, night or automatic operation, although not every installation uses all of these. Humidity, presence or timer controls may affect speed, so the test condition and any override used should be recorded rather than guessed.
How airflow testing is carried out
The person commissioning the system uses a method and instrument suited to the terminal and system. In broad terms, the instrument captures or samples air moving through the grille or valve and reports a flow rate. The relevant government guidance sets out approved procedures for work within its scope; competent installers also follow the equipment instructions and project design.
- Identify the terminal and room. Each measured point should be traceable on the record, not listed as an anonymous reading.
- Put the system into the required mode. Continuous systems may require normal and boost readings. The mode must be explicit.
- Use the instrument correctly. The test hood, vane anemometer or other device must suit the application and be used in a way that does not create a misleading result.
- Compare the reading with the design or applicable guidance. A number without its target and units has limited value.
- Adjust and repeat where needed. Central systems may require balancing so that changing one terminal does not leave another under-supplied or over-extracted.
- Record the final condition. The report should represent the settings handed over, including relevant fan speeds, valve positions or control information.
For mechanical ventilation work covered by Regulation 42 of the Building Regulations 2010 in England, the person carrying out the work must ensure that airflow-rate testing is completed in accordance with an approved procedure and that results are notified to the local authority in the prescribed way. Whether a particular alteration falls within that duty depends on the work and regulatory route, so project teams should confirm the position with their building control body rather than applying a blanket assumption.
Useful questions while the system is being tested
- Which drawing or design values are the readings being compared with?
- Are normal and boost modes both relevant to this installation?
- Were all terminals measured and clearly identified?
- Were door undercuts, background ventilators and other air paths in the intended condition?
- Did adjustments to one terminal affect readings elsewhere?
- Will the final settings be protected from accidental alteration?
How to read an airflow commissioning record
A useful record connects each measurement to a place, operating mode and target. Units should be stated. It should be possible for a future contractor to understand what was installed, what was measured and which settings were left in service.
| Record item | Why it matters | Question to ask if it is missing |
|---|---|---|
| System and fan identification | Links the result to the actual equipment and property. | Which model and ventilation strategy were tested? |
| Room and terminal reference | Shows where each reading was taken. | Can each result be matched to a visible terminal? |
| Operating mode | Distinguishes normal, boost or another relevant condition. | Which control state produced this reading? |
| Design value and measured value | Allows the result to be assessed rather than viewed in isolation. | What target was used and where did it come from? |
| Instrument and test details | Provides basic traceability for the measurement. | Was the method suitable for this terminal? |
| Final settings and comments | Records balancing, unusual constraints and the handed-over condition. | Were adjustments completed and retested? |
Do not compare one household’s figures casually with another property. Required performance depends on the building, rooms, system type, occupancy assumptions, design and applicable guidance. A commissioning sheet is most useful when read against the information for that installation.
A note on current Approved Document F editions
As at October 2026, the government’s 2021 edition of Approved Document F remains relevant to work under its transition arrangements. A 2026 edition has been published, with later coming-into-force dates stated by government: 24 March 2027 for work not connected with higher-risk building work and 24 September 2027 for work connected with higher-risk building work. Earlier editions can continue to apply to projects covered by their transition provisions. Always confirm which version governs the specific project.
Why an installed system may miss its intended airflow
A low or unstable reading is a reason to investigate the system, not simply increase speed and walk away. Higher speed may increase noise or energy use without correcting the underlying restriction.
- Duct resistance: excessive length, tight bends, unsuitable components or crushed flexible duct can restrict flow.
- Incomplete air paths: missing or closed background ventilators and restricted transfer paths can affect the whole strategy.
- Terminal adjustment: an over-closed valve may limit one room, while an over-open valve can disturb balance elsewhere.
- Obstruction or contamination: packaging, debris, dirty filters or blocked external grilles can reduce performance.
- Control configuration: the measured mode may not be the intended mode, or a sensor and override may be interacting unexpectedly.
- Design or installation mismatch: changed routes, substituted equipment or an overlooked property constraint may require a competent review.
The corrective action should address the cause and be followed by a repeat test where appropriate. Cosmetic completion should not take priority over an unresolved performance issue.
What should happen at handover?
Commissioning is only complete when the relevant information reaches the people who operate and maintain the system. The handover should identify the ventilation strategy, explain normal and boost operation, show which controls residents should use, and describe safe routine maintenance. It should also make clear who to contact about defects or unusual behaviour.
Keep the airflow test record with the installation information. AEG’s broader guide to the retrofit handover pack explains how commissioning sheets fit alongside scope records, manuals, guarantees and maintenance guidance. If a bathroom fan later seems to run constantly, first compare its behaviour with the commissioned mode; the guide to a bathroom extractor fan that keeps running covers that separate operating question.
Frequently asked questions
Does every ventilation fan need the same airflow test?
No. The suitable procedure depends on the system, scope and applicable requirements. An intermittent extract fan and a whole-house ducted system have different operating modes and balancing needs.
Can I test airflow with a piece of paper or tissue?
That may indicate that air is moving, but it does not provide a reliable commissioning measurement or confirm that a design value has been achieved. Use an appropriate instrument and method.
Should commissioning happen before decorating is finished?
The system should be complete and in a representative condition for its final test. If later work changes terminals, ducts, controls or air paths, the affected performance may need to be checked again.
What if the measured airflow is lower than the design value?
The installer should investigate the system, correct the cause where possible and repeat relevant measurements. Simply increasing fan speed may not be the right solution.
Is a commissioning sheet the same as a user manual?
No. A commissioning sheet records system-specific checks, results and settings. A manual explains the product. Both can be useful, together with a clear demonstration of the controls.