Pre-Construction Information: What Should Be Shared Before Building Work Starts?

Useful project information needs to reach designers and contractors early enough to influence decisions. This guide explains what pre-construction information is, who uses it and why a generic folder is not enough.

PurposeGive designers and contractors relevant information about the project, site and foreseeable risks.
TimingProvide it early enough for tendering, design and construction planning, then update it as knowledge changes.
Important limitIt is not the construction phase plan, a generic risk assessment or the finished health and safety file.

Pre-construction information is the project-specific information that designers and contractors need so they can plan, price, design and organise construction work with health and safety in mind. It may draw on surveys, existing records, the client brief, design information and what is known about the site and its surroundings.

The phrase comes from the Construction (Design and Management) Regulations 2015, usually called CDM 2015. The regulations apply to construction work, including domestic projects, although the way client duties are carried out differs between domestic and commercial clients. Good pre-construction information is therefore not a decorative compliance document. It is a working set of relevant facts and decisions that should become clearer as the project develops.

Short answer: useful pre-construction information tells the project team what is being built or changed, what is already known about the property and site, which significant risks or constraints may affect the work, and what information still needs to be obtained. It should be proportionate to the project and easy for the people who need it to use.

Pre-construction information, construction phase plan and health and safety file

These three terms are related, but they describe different information at different stages. Treating them as interchangeable creates gaps and duplication.

Information setMain purposeWhen it is used
Pre-construction informationProvides relevant project, site, design and risk information to designers and contractors.During briefing, design, tendering and preparation for construction; updated when new information emerges.
Construction phase planSets out the health and safety arrangements, site rules and relevant specific measures for managing the construction phase.Prepared before the construction phase begins, then reviewed and revised during the work.
Health and safety fileRetains information about the project that is likely to be needed to protect people during later construction work.Prepared and developed on projects involving more than one contractor, then passed to the client at completion.

HSE explains that the principal contractor prepares the construction phase plan on a project involving more than one contractor; the contractor does so on a single-contractor project. Pre-construction information and key design information help shape that plan. The plan should not be a copy of the pre-construction information: it must explain how the construction phase will be managed.

The health and safety file also has a narrower future-facing purpose. It should contain information likely to be needed for subsequent construction work, not every contract document, email or general site record. A separate AEG guide explains the broader retrofit handover pack, which can include operating instructions, commissioning records, warranties and maintenance information beyond the CDM health and safety file.

Architect reviewing drawings and project information before construction
Project information is useful when it is checked, coordinated and connected to real design and site decisions. Photograph by Daniel McCullough via Unsplash; held in AEG’s Media Library.

Who brings the information together?

Commercial clients

HSE states that commercial clients must provide pre-construction information to every designer and contractor who is bidding for the work or has already been appointed. The client does not need to personally author every technical item, but must make suitable arrangements for the project and ensure that relevant existing information is made available.

Principal designers

Where a project involves, or is likely to involve, more than one contractor, the client appoints a principal designer to take control of the pre-construction phase. HSE describes helping and advising the client in bringing together pre-construction information—and providing the information designers and contractors need—as part of that role. The principal designer also coordinates the design work and liaises with the principal contractor about risks that need to be managed during construction.

Designers and contractors

Designers must take account of the information supplied, eliminate foreseeable risks where possible and reduce or control those that remain. Contractors use the information to plan the work, assess resources, develop construction methods and prepare the construction phase plan. They should also raise gaps or contradictions rather than silently guessing.

Domestic clients

CDM 2015 applies when a homeowner arranges construction work on their own home, but HSE explains that domestic client duties normally pass to the contractor on a single-contractor project or to the principal contractor where more than one contractor is involved. A domestic client can instead agree in writing for the principal designer to carry out the client duties. Homeowners should still provide information they hold—such as previous surveys, asbestos records, service information or details of known problems—and allow the project team suitable access and time.

Appointments matter. On a project involving more than one contractor, the principal designer and principal contractor are distinct CDM roles. Job titles alone do not settle who is performing them. The written appointments, project structure and HSE guidance should be checked for the actual job.

What might pre-construction information include?

There is no useful one-size-fits-all contents list. A short repair in an empty property will not need the same information as a major refurbishment in an occupied block. The information should reflect the scope, complexity and foreseeable risks. Depending on the project, relevant items may include:

Project brief and scopeThe intended work, objectives, boundaries, phasing, design assumptions, client requirements and known exclusions.
Existing property informationAvailable drawings, previous alterations, structural information, surveys, maintenance records and an existing health and safety file.
Site and access constraintsAccess routes, delivery limits, working hours, storage, welfare, security, neighbours, shared areas and emergency access.
Existing servicesKnown electricity, gas, water, drainage, heating, communications and other services, including available isolation and location information.
Hazardous materials and conditionsRelevant asbestos information, contamination, fragile surfaces, structural instability, confined areas or other significant existing hazards.
Occupancy and interfacesResidents, staff, visitors, vulnerable occupants, adjacent businesses, public routes and other contractors whose activities may interact with the work.
Design and construction risksSignificant or unusual residual risks, sequencing constraints, temporary works assumptions and details needing specialist coordination.
Information and handover requirementsRequired inspections, test records, concealed-work evidence, product records, commissioning data and future maintenance information.

For older buildings, the information may need to identify investigations required before intrusive work. AEG’s guide to asbestos checks before retrofit explains why the work area and planned disturbance matter; a generic historic survey may not answer the question for a new scope. Likewise, product information such as a safety data sheet has a different job. The AEG guide to construction safety data sheets explains how supplier information must be connected to the actual task through assessment and controls.

Make the information specific, proportionate and usable

A long document is not automatically a good one. The aim is to help the recipient make better decisions. Information should be current, traceable and organised so that significant matters are easy to find.

Define the project and recipientsIdentify the work, project stages, likely contractors and decisions the information needs to support.
Gather what already existsCollect relevant records from the client, building owner, facilities team, previous projects and available surveys.
Check relevance and reliabilityConfirm which area, date and scope each record covers. Mark information that is incomplete, historic or based on an assumption.
Identify missing informationArrange proportionate surveys, investigations or specialist input where a decision cannot safely be made from the existing evidence.
Issue and explainProvide the information early enough for design and tender decisions, highlight significant items and record who received each revision.
Keep it liveUpdate the set when the design, site conditions, occupancy, sequence or known risks change, and pass relevant developments to the principal contractor.

Where work takes place in occupied homes, information about access, communication, temporary services, security and resident needs can affect the method and programme. AEG’s guide to whether residents can stay home during retrofit work explores those practical interfaces in more detail.

Construction project planning and coordination before site work begins
Early coordination helps project information influence design, procurement, logistics and site delivery rather than arriving after decisions have been fixed.

Common weaknesses to avoid

A generic template with no project evidence

A template can help structure the work, but standard wording does not reveal the services in a wall, the occupancy of a building or the limitations of a survey. Replace prompts with property-specific information and record genuine gaps.

Information issued too late

If a survey arrives after the design and price are fixed, the team may have to redesign, delay work or manage a risk that could have been removed earlier. Issue available information during tendering and design, then update it rather than waiting for a supposedly perfect final pack.

Unlabelled assumptions

Not every condition can be confirmed before work starts. Assumptions should be visible, linked to a verification action and owned by someone. Presenting an assumption as fact can mislead designers and contractors.

Dumping every document into one folder

Old drawings, duplicate surveys and irrelevant manuals can hide the information that matters. Use an index, clear filenames, revision dates and short explanations of scope. Superseded information should be controlled so that it is not mistaken for the current position.

Failing to record change

Opening-up may reveal different construction, services may be rerouted, residents may remain in an area longer than expected or the sequence may change. The project team should review what the new information means for design and construction planning, not simply file the photograph.

Questions clients can ask before work starts

  • Who is the principal designer and, where applicable, the principal contractor?
  • Which existing drawings, surveys and records have been checked?
  • What important information is still missing, and who will obtain it?
  • Which assumptions could change the design, price, programme or method?
  • How will information reach every designer and contractor who needs it?
  • How are revisions identified so that the current version is clear?
  • Has occupancy, access, neighbouring property and public protection been considered?
  • How will new findings during opening-up or installation be reviewed and shared?
  • Which records must be captured before work is concealed?
  • What will feed into the construction phase plan and the final health and safety file?

Frequently asked questions

Is pre-construction information required for a small domestic project?

CDM 2015 applies to construction work, including domestic projects, but the information should be proportionate to the work and risks. Domestic client duties normally pass to other dutyholders as HSE describes. A modest job may need a concise set of relevant information rather than a large formal dossier.

Who writes the pre-construction information?

The information is usually assembled from several sources. The commercial client provides information they hold, while the principal designer helps and advises the client in bringing it together on projects involving more than one contractor. Designers, contractors and specialists contribute relevant information and identify gaps.

Is it the same as a pre-start meeting?

No. A pre-start meeting can be a useful way to discuss and confirm information, responsibilities and changes, but it does not replace the project information itself. Decisions from the meeting should be recorded and issued to the people affected.

Does it need to include every possible site hazard?

It should provide relevant information about the project and significant foreseeable risks, proportionate to the work. It is not improved by copying generic hazard lists that do not help design or construction decisions. Contractors still have their own duties to plan and manage their work.

What happens if new information is found after work starts?

The relevant dutyholders should assess what it changes, update affected information and communicate it to those who need to act. The construction phase plan, design, sequence or controls may also need review. A live change record is more useful than leaving the original pack untouched.

Authoritative guidance

This article provides general information about the CDM planning process. Project roles, appointments and information requirements should be confirmed for the actual scope with competent project advisers and current HSE guidance.

Planning coordinated construction work?